Construction Progress at Amur GPP in July 2020 Achieves 64.2%.
Large-capacity equipment for the fourth process train has been delivered to the temporary jetty of the Amur GPP. Gas separation columns were transported to the construction site mainly at night to ensure proper traffic safety. Readiness for installation of the main process equipment of the fourth train is fully ensured.
Commissioning is underway at the first start-up complex (first and second lines). Compressor station systems of the first process line are being handed over for oil flushing. Process pipelines are being tested.
Steel structures are being erected for the third and fourth lines. Commissioning activities are underway in the main distribution substation and at the power facilities. Operations on the priority gas metering units are nearing completion.
Construction of the medical center with a modern CT and PCR laboratory complex is complete.
#AmurGPP#GazpromPererabotkaBlagoveshchensk#Svobodny
Мы используем cookie-файлы, чтобы улучшить сервисы для вас. Если ваш возраст менее 13 лет, настроить cookie-файлы должен ваш законный представитель. Больше информации
Комментарии 1